Providing solutions to global brands.

Working for Insite Contracts to client Sitel, a global customer contact centre to deliver an installation project at their Maxim 10 site in Motherwell to challenging timescales.

Maxim 10 Building

AKD were brought in to carry out Category A & B fit-out works, installing a 650kva Standby Generator, 80Kva UPS system, the reworking of the mains power distribution, with full power, structured cabling, LED lighting and Fire & Security systems throughout the four-storey office premises.

Following the early handover of the ground floor, we went on to work within an operational building with the client taking possession of the ground, 1st, 2nd and then finally the 3rd floor in quick succession.

AKD started Maxim 10 in August 2018 and completed in March 2019, it was a successful project all round.